Corporate Focus - February 2010
Sky’s the Limit
The long-awaited judgment in the BskyB Limited (“Sky”) v
Electronic Data Systems Limited (now part of Hewlett-Packard)
(“EDS”) case has finally been handed down by the Technology and
Construction Court (“TCC”). It has confirmed the worst fears of
many IT suppliers and has potentially global implications for the
industry.
Background
Following a lengthy tender process in 2000, Sky selected EDS to
design, build, manage, implement and integrate its new customer
relationship management system (“CRM”).
The relationship floundered. In 2001 Sky and EDS amended the
main contract to extend the project timetable. However, the
difficulties continued and in 2002 Sky terminated the contract and
brought a claim for damages for over £700 million.
The Claim
Sky claimed that:
- EDS had made fraudulent misrepresentations in relation to
resources, cost, time, technology and methodology during the tender
process and these misrepresentations had led to Sky awarding EDS
the CRM system project and entering into the initial contract;
- EDS had made negligent misrepresentations in relation to
progress to date, resources, planning, and cost, and these
misrepresentations had led to Sky varying the contract;
- EDS was in breach of a number of its obligations under the
initial contract and that such breaches amounted to a repudiatory
breach of the initial contract.
Damages awarded for fraudulent and negligent misrepresentations
are recoverable whether foreseeable or not. The duty to mitigate
loss is still applicable, however.
If Sky proved the allegations of misrepresentation therefore,
the contractual liability cap of £30 million would not apply.
The Decision
The TCC found that:
- EDS had made fraudulent misrepresentations in relation to the
time it required to complete and deliver the project within the
promised timescales. Sky’s other allegations were not upheld.
- EDS had made negligent misrepresentations in relation to
planning prior to entering into the contract variation and such
misrepresentations had induced Sky to enter into the
variation.
- Whilst the ‘Entire Agreement clause’ EDS sought to rely upon in
its defence, was ineffective to exclude liability for negligent
misrepresentation, TCC held its liability was subject to the
overall contractual liability cap.
- EDS were held to be in breach of the initial contract; however
these breaches were not of a repudiatory nature. EDS's liability
for breach of contract was subject to the overall contractual
liability cap.
- Sky had not failed to mitigate its losses by implementing the
CRM itself.
Damages are still to be assessed; however the Court has ordered
EDS to make an interim payment of £200 million. It is thought the
final damages will be around £400 million.
The decision is likely to be appealed.
Implications
Understandably, this case has attracted a lot of attention
within the IT industry. The sums of money involved are vast- legal
fees alone are estimated at £70 million. However, it is hard to see
how the facts and the circumstances of this case could be
replicated in order to reproduce a decision like this.
Sky was resourceful in that it was able to produce documentary
evidence that EDS’s representations at tender induced them to enter
into the initial contract. Sky was also able to show that, had EDS
not made such representations, it would have engaged the services
of Pricewaterhouse Cooper.
In Court, Sky’s barrister was able to show that EDS’s Managing
director (the man who made the representations to Sky at tender)
had been dishonest about his MBA degree. It was discovered that he
had not attended university, but had bought the degree online.
Arguably this enabled Sky to establish EDS had been deceitful in
its claims made at tender something which could not have been done
otherwise.
Despite this, the case does serve to highlight two important
areas which IT suppliers should not overlook:
- Greater awareness of the methods employed by their workforce
when tendering for work is needed (checks on qualifications senior
staff purport to have could also prove invaluable!). Only
considered and rational promises should be made to prospective
customers in relation to, amongst other things, their costings and
ability to deliver the product and/or services within timescales.
If problems are encountered, an open and honest approach with
customers, to effectively manage their expectations, may reduce the
risk of litigation. EDS maintained to Sky throughout that progress
was going according to plan, whilst internal memos demonstrated
this was simply not the case.
- A review of the “entire agreement clause” contained within
standard terms and conditions should be undertaken. The clause
needs to be drafted so that it will cover negligent
misrepresentations. Case law has shown that such a clause will be
upheld; however in EDS’s case, its clause was insufficient.
Customers should think about keeping a detailed record of their
selection process including evidence which shows where reliance is
made on statements made during pre-contractual discussions. They
may also start to ask for evidence to support statements made
during any tender process, in particular in relation to timescales
for delivery.
If you have any questions in relation to fraudulent or negligent
misrepresentations, or would like guidance on your “entire
agreement” clause, please contact Sean Crotty, Partner in our
Corporate team on 0151 242 6517 or sean.crotty@weightmans.com