The Weightmans website would like to use cookies to store information on your computer to improve our website. To find out more about the cookies we use and how to delete them, see our privacy policy.

Newsletters

Local Government - March 2009


Construction law update

In this update we highlight three construction law cases dealing with:

  • The need to notify insurers promptly
  • The effect of delay in a project involving sectional completion
  • Adjudication and oral contracts.

Don’t keep it to yourself
The recent decision in the case of Aspen Insurance UK v Pectel highlights the pitfalls faced by contractors and consultants when deciding whether to notify insurers about problems which might give rise to a claim later on.

The facts are these. Pectel, a specialist in the removal of  asbestos from underground facilities, was engaged by Amec in February 2004 to strip two deep-level tunnels beneath Manchester which were used by BT for its telecommunications network. Preparatory work in the cross-over section between the tunnels was suspended  briefly towards the end of March that year, during which time a fire broke out, causing  extensive damage costing approximately £15m to put right.  The fire started in a fluorescent light fitting, damaged by Pectel during its preparatory work. The fire’s destruction was  exacerbated by the flammable polythene sheets being used by Pectel to limit the spread of asbestos dust. The sheets did not meet the required specification, but that was not known at the time.  BT and Amec started an investigation into the cause of the fire straight away. They removed Pectel’s equipment for testing and got their lawyers to interview Pectel’s employees. Pectel asked Amec whether it should be worried. Amec said no. Six months later, however, BT obtained a report which condemned Pectel’s materials. BT asked Pectel to explain how it  intended to overcome “this serious issue”. Pectel did not provide a satisfactory answer.  The matter then went quiet until November 2006, when BT informed Amec that a claim was  imminent.  Amec’s lawyers wrote to Pectel suggesting that Pectel notify its insurers. Pectel ignored the letter. A few months later, BT served its letter of claim upon Amec, blaming Pectel  for the fire. Pectel passed a copy to its broker on 9 March 2007. The broker finally told Pectel’s insurers about the claim two weeks later.  Pectel had public liability cover with Aspen (and other insurers). It was required to give the insurers “immediate” written notice of any occurrence which might give rise to a claim, and the insurers’ obligation to indemnify was conditional upon, amongst other things, observance by Pectel of all the policy’s terms and conditions. The insurers refused to cover the claim, citing Pectel’s failure to comply with those policy requirements.  Pectel challenged the insurers’ decision in the commercial court, relying principally on Amec’s statement made in April 2004 that Pectel had nothing to worry about.

The judge decided the insurers were right. It was common ground that “immediate” notice meant “with all reasonable speed considering the circumstances of the case”. The fire had been very serious and the repair  costs substantial. The investigation into what started the fire focused upon Pectel’s work and equipment and t the time of Amec’s reassuring statement to Pectel, a cause had not then been identified. In fact, the investigation was barely underway.

In short, Pectel was wrong to have relied upon Amec’s statement alone and ignored everything else going on around it. In the judge’s view, a reasonable man would have been unable to  dismiss the possibility that the fire was in some way connected with Pectel’s work. There was therefore a real possibility that a claim might be brought against Pectel in due course and that  in order to protect itself, Pectel would seek an indemnity from its insurers. Accordingly, the judge concluded that Pectel should have given written notice to its insurers of the fire and a possible claim by early April 2004.

Does that sound harsh? Well, you might think so, but bear in mind why the insurers’ obligation to pay out was conditional upon immediate written notice of a possible claim. The same or similar language is common in most insurance policies and it is intended to provide insurers with an opportunity  to investigate a potential claim promptly and to take action to  minimise the extent of any required indemnity.  So, don’t make the same mistake as Pectel. If  something goes wrong on a project, ask yourself this question: is there a real possibility I might get caught up in a claim (even if I believe that I am not at fault)? If the answer is yes, it would be wise to notify your insurers straight away.

Roll up, roll up: the penalty for delays in sectional completion agreements
A recent case, Liberty Mercian Limited v Dean Dyball Construction Limited, clarifies the effect of delays in projects procured on a sectional completion basis.

Liberty retained Dyball to build a handful of new retail units, dividing the work into five sections, each with its own completion date. Section 1 was delayed, for which Dyball claimed an eight-week extension of time (EoT). However, Liberty only granted four weeks, alleging culpable delay by Dyball for the rest, and so it deducted liquidated damages (LADS).

The parties fell out over the effect of the delay on sections 2 to 5. Liberty awarded a further four weeks for each subsequent section (reflecting EoT for section 1) but ignored Dyball’s four-week culpable delay, thereby jeopardising the completion targets for the later sections and exposing Dyball to further deductions for LADs.

Dyball argued that it was entitled to a full eight-week EoT for each subsequent section, that the sectional completion agreement effectively created a series of separate mini-contracts and that the cause of the section 1 delay was thus irrelevant. In short, if the section 1 delay was rolled into sections 2 to 5 and LADs repeatedly applied, that would penalise Dyball unfairly.

A persuasive argument? No said the Judge, because a reasonable person would infer that delay to section 1 must inevitably render late the commencement of the later sections. While the contract did not state expressly that any culpable delay to section 1 should be rolled into the later sections that must have been the parties’ intention. There would be no sense whatever in construing a sectional completion agreement any other way. Dyball’s delay clearly had a knock-on effect and thus logically it was for additional LADs. To find otherwise would allow Dyball to benefit from its default, which could not be right.

A harsh result? Look at it this way. Sectional completion is often adopted for high-yield projects like distribution centres, facilitating a rapid response by the end-user to changes in consumer demand and allowing key facilities to be prioritised and delivered promptly. But the other components of the build cannot be ignored if it is to function satisfactorily as a whole. The contractor’s task is therefore harder: not only does he have to meet a series of deadlines for delivering parts of the jigsaw he has to ensure that all those parts piece together as a whole on time as well. His opportunity to claw back any slippage is consequently limited and so caution, not to mention thorough forward programming, are essential.

Changes in Adjudication…what’s all the fuss about?
Of all the proposed changes to the Housing Grants, Construction & Regeneration Act 1996, none is proving more controversial than the prospect of seeing the statutory scheme for adjudication applied for the first time to oral construction contracts.

Commentators argue that the changes will give way to lengthy, contested hearings with conflicting witness evidence, and, ultimately, a greater number of challenges to adjudicators’ decisions in Court. In short, can adjudication remain workable within the usual 28-day format, or even the extended 42-day version for that matter, if oral contracts are brought within its scope? 

Judge Bowsher in the well-known Grovedeck case clearly thought not: “Disputes as to terms, express and implied, of oral construction agreements are not readily susceptible of resolution by summary procedure such as adjudication”. His view was later echoed by the House of Lords in another well-known case, RJT Consulting Engineers: “That is why a record in writing is so essential. The written record of the agreement is the foundation from which a dispute may spring but the least the adjudicator has to be certain about is the terms of the agreement which is giving rise to the dispute…”. 

But will this change really complicate things? The recent case of Euro Construction Scaffolding Ltd v SLLB Construction Ltd might give a clue. 

Euro asked the Court to enforce a decision in its favour requiring SLLB to pay for various scaffolding works that Euro had implemented to assist SLLB’s construction of a basement swimming pool. The scaffold had collapsed, causing SLLB to argue that it had not been fit for its intended purpose, which was to support the sides of the excavation, even though Euro had assured SLLB during a telephone conversation that it “could” provide a sufficiently robust solution to hold back the earth. SLLB contested the adjudicator’s jurisdiction to decide the matter on the ground that Euro’s assurance created an express oral term of the contract. However, a letter written by SLLB to Euro later in the project suggested that this conversation had been far less specific and that Euro had merely been asked to confirm whether it could build a “birdcage” scaffold.

SLLB’s order had been placed orally and it had no documentary evidence to prove what, if any, requirements had been made known to Euro. On the other hand, Euro’s quotation for the works, which was in writing, was not consistent with any requirement that the scaffold should support the sides of the pool excavation. 

Judge Akenhead, who heard the case, decided that the Adjudicator had been right to dismiss SLLB’s evidence. First of all, even if Euro had said that it “could” provide a solution to retain the earth that was not the language of agreeing an express term. If Euro had said that it “would” provide the required solution then that might have changed things. Secondly, there was real force in the view that other documents available to him contradicted any suggestion by SLLB that it had told Euro the scaffold needed to support the sides of the swimming pool. The duty was therefore on SLLB to show that it had a real prospect of establishing that an oral term had been agreed but it had not done so.

Let’s be realistic then. Arguments about contractual terms are nothing new, although their focus has tended in the past to be upon whether all the express terms of an agreement are recorded in writing. But that kind of wrangling, to which adjudicators are used to and adept at resolving, is not really any different from an enquiry to determine the terms of an entirely oral contract. Adjudicators have been and will no doubt continue to be robust in their decision making and where common-sense dictates, we can expect their decisions to be upheld by the Court.  Resistance to change is always inevitable but scratch beneath the surface a little and there really does seem to be a lot of fuss about nothing where this particular change is concerned.

Ed Lewis, Partner
Weightmans LLP