London Market - December 2009
Contractor’s agreement, asbestos, damage to property
In Corus UK Ltd v Cavendish (UK)
Ltd & Others (7 August 2009) the
claimant claimed damages against the first defendant contractor and
the third defendant sub-contractor in respect of the removal of
asbestos at office premises owned by the claimant. The
contract was for the removal of ceilings that had been sprayed with
asbestos, although there was overspray on the concrete beams above
the ceiling that was to be covered with a sealant rather than
removed.
Removal of the ceilings proved impractical due
to their construction. The contractor suggested a revised method
involving leaving the old ceiling, scraping the asbestos from it
and installing a suspended ceiling underneath the older one.
Sub-contractors carried out the works under the original
contractor’s supervision.
Asbestos debris was found some ten years later
in-between the old and new ceilings. It was agreed that the debris
had probably been caused by the dragging of electrical cables over
the old ceiling, which had resulted in the debris falling through
the lighting wells onto the new ceiling.
The claimant sought to recover the cost of
remedial works and argued that:
- The advice from contractors had been
inaccurate or misleading because under the revised method asbestos
would be left on the underside of the old ceiling
- Both contractor and sub-contractor were in
breach of their duty of care in tort in failing to exercise
reasonable skill and care in their removal of the asbestos coated
materials by leaving them in situ in a loose and disturbed
condition
- The contractor owed a concurrent duty of care
in tort to exercise reasonable skill and care in providing the
services it had contracted to provide and was obliged to avoid
causing economic loss and physical damage in doing so.
Held
The claimant’s
claims were discussed:
- It had been known that not all of the
asbestos would be removed. The contractor would not have
given a guarantee that every trace would be removed.
- The works had been carried out in a competent
manner. The debris was not from the underside of the older
ceiling, it had been caused by the dragging of cables causing
debris to fall through fittings.
- Even if the work had not been carried out
competently, it could not be said to have damaged the
property.