Marine & Transit - April 2010
"Achilleas" revisited: damages for loss of sub charter
Sylvia Shipping Co Ltd v Progress Bulk Carriers Limited
(The "Sylvia") - Commercial Court (Hamblen J)
[2010] EWHC 542 (Comm)
This arbitration appeal to the Commercial
Court provides a useful reminder of the possibly limited
ramifications of the House of Lords decision in The
“Achilleas” [2009] 1AC 61, following the initial
hullaballoo caused by the judgment, in connection with the
recoverability of damages for the loss of a charter party
fixture.
It will be recalled that decision concerned a
vessel under a time charter being redelivered nine days late, which
resulted in owners losing a lucrative fixture albeit re-fixing with
the same charterer at a much lower rate. Owners’ claim for damages
for loss of fixture profits failed, and was instead limited to the
traditionally understood measure of the difference between the
charter and market rates for the period of overlap.
Two of the judgments (Lord Roger, Baroness
Hale) followed the traditional Hadley v Baxendale
reasoning i.e. that loss of a particularly lucrative fixture was
too remote to be recoverable, not being a loss the parties would
contemplate as likely to follow from the breach, whilst two Law
Lords (Hoffman and Hope) applied a more novel, broader approach
based upon the parties’ assumption of risk, which Lord Walker
tacitly approved.
The circumstances in The
“Sylvia” were superficially similar, albeit with roles
reversed and here charterers were claiming from owners damages for
loss of fixture.
The vessel had been period time chartered by
owners to Progress who, in turn, had sub chartered to Conagra for
the carriage of the cargo of wheat from Quebec to Casablanca.
However, port state control rejected the fitness of the vessel for
loading. The time taken to complete de-scaling and repairs
meant that the sub charter laycan overran and Conagra cancelled.
Progress managed to arrange a substitute charter but for a less
favourable rate.
It was agreed that owners were in breach of
their contractual maintenance obligations, and the question to be
determined by the tribunal and the Commercial Court on appeal was
the recoverability of charterers’ loss.
Predictably, owners contended that The
“Achilleas” decision meant that Progress’s claim was
limited to the difference between the charter and market rates
during the 7 day period of delay. However, the Court agreed
with the tribunal’s assessment that Progress was entitled to
damages based on the loss of the Conagra charter less receipts for
the substitute fixture: a recoverable loss of about US$273,000.
In so deciding, Hamblen J. made a number
of observations:
- Owners’ argument that they had not “assumed
the risk” of this type of loss (i.e. the novel
“Achilleas” approach) was misconceived.
- The “Achilleas” was an
amalgam of orthodox (Hadley v Baxendale) and
broader approaches, but in the great majority of cases it was
unnecessary to address the issue of assumption of responsibility.
The House of Lords decision concerned unusual circumstances, a
volatile market, and a background of market expectation of
liability being restricted in specific late redelivery
situations.
- Usually the fact that the type of loss arises
in the ordinary course of things or out of special circumstances
will carry with it the necessary assumption of responsibility.
Therefore Hadley v Baxendale remained the standard
rule which was to be applied in most cases.
- There was nothing unusual or extraordinary
about this case. There was authority that loss of a sub charter was
recoverable: The “Derby” [1984] 1 Lloyd’s Rep 635,
and there was no market understanding to the contrary.
- Further the liability was not unquantifiable,
uncontrollable or disproportionate. Owners would expect the vessel
to be sub chartered, the period for which could never be for longer
than the time charter itself. The loss was therefore within
reasonable and fixed confines. As such, it was foreseeable, and
therefore recoverable.
This case underlines the fact that The
“Achilleas” dealt with a discrete issue and was a case
very much on its own facts. The traditional contractual
approach to recoverability of contractual damages is therefore
undisturbed. In this case, it was easily foreseeable that if the
vessel was not fit to load upon presentation, that this could have
adverse implications for any sub charter, and cancellation was an
ordinary consequence of breach.