Marine & Transit - April 2010
Port or berth charter - Who pays for delay?
Novologistics Sarl v Five Ocean Corporation (The
“Merida”) – Commercial Court (Gross, J.) [2009] EWHC 3046
(Comm)
As between owners and charterers, who is
responsible for delay in loading a vessel following its arrival at
the load port? Under established charter party law, if there
is a port charter, the owners are entitled to tender notice of
readiness (NOR) immediately upon arrival at the port and any delay
thereafter will be for the charterer’s account. On the other
hand, if there is a berth charter, NOR cannot be tendered until the
vessel actually berths at a berth within the port and any delay
incurred waiting for a berth will be for the owner’s account.
This issue arose in The
“Merida”, a case on appeal to the Commercial Court from a
London arbitration. Gross J had to decide whether the charter
was a port charter or a berth charter and accordingly which of
owners or charterers was responsible for delay in loading at the
load port due to congestion.
The charter party was for the carriage of a
cargo of steel plates from China to Bilbao and Cadiz in Spain. The
vessel arrived at the Chinese load port of Xingang and immediately
tendered NOR. The vessel then anchored awaiting a berth. However
due to congestion at the port the vessel did not berth for some 20
days. The owners accordingly pursued a claim for demurrage of about
US$500,000 for the resultant delay in the vessel’s loading.
The charter party was based on a “recap” which
rather unusually did not refer to a previous pro-forma charter
party. The charter included the following terms:
One good and safe chrts’ berth
terminal 4 stevedores Xingang to one good and safe berth Cadiz and
one good and safe berth Bilbao - (described by the Judge as the
“opening term”)
clause 2
[1] The vessel to load at one
good and safe port/one good and safe charterers’ berths Xingang and
to discharge at one good and safe port/one good and safe
charterers’ berth Cadiz and at one good and safe port/one good and
safe charterers’ berth Bilbao.
[2] Shifting from
anchorage/warping along the berth at port of load and at ports of
discharge to be for owners’ account, while all time used to count
as lay time.
The arbitrators had found that the wording of clause 2 provided for
a port charter, as primarily it referred to both safe ports and
berths and also the shifting time provision allowed for the master
to tender NOR once the vessel arrived at the port, as had in fact
occurred.
Following review of the authorities however,
Gross J came to the opposite conclusion, deciding that the
arbitrators had erred in finding that there was a port
charter. He considered that the charter was in fact a berth
charter.
It was necessary to identify what was the
“specified destination” under the charter (The “Johanna
Oldendorff” [1974] AC 497) and whether that destination
was the port or was a berth within the port (The “Radnor”
[1955] 2 LLR 668, The “Finix” [1975] 2 LLR 415 and
The “Puerto Rocca” [1978] 1 LLR
252).
In this case the Judge ruled that the opening
term of the charter identified the destination as the berth at
terminal 4 at the port of Xingang. The judge further held
that clause 2 did not qualify the opening term so as to turn the
charter into a port charter. The clause merely introduced a
safe port warranty that reiterated the existing safe berth warranty
provided for in the opening term. The judge therefore allowed
the charterer’s appeal with the consequence that the owner’s claim
for demurrage failed.
The case illustrates that owners and
charterers must consider very carefully the precise wording
introduced into such lay time clauses when negotiating the charter
party contract.